[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893363":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893363,580,1,"单选题","采用锤击法打预制钢筋混凝土桩，方法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","桩重大于2t时，不宜采用“重锤低击”施工",false,{"key":16,"text":17,"correct":18},"B","桩重小于2t时，可采用1.5～2倍桩重的桩锤",true,{"key":20,"text":21,"correct":14},"C","桩重大于2t时，可采用桩重2倍以上的桩锤",{"key":23,"text":24,"correct":14},"D","桩重小于2t时，可采用“轻锤高击”施工","实践证明，桩重小于2t时，当锤重大于桩重的1.5～2倍时，能取得良好的效果，但桩锤也不能过重，过重易把桩打坏；当桩重大于2t时，可采用比桩轻的桩锤，但亦不能小于桩重的75%。这是因为在施工中，宜采用“重锤低击”，即锤的重量大而落距小，这样，桩锤不容易产生回跃，不致损坏桩头，且桩易打入土中，效率高；反之，若“轻锤高击”，则桩锤容易产生回跃，易损坏桩头，桩难以打入土中。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]