[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893359":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893359,580,1,"单选题","钢筋混凝土预制桩的混凝土达到其设计强度的（ ）后方可起吊。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","50%",false,{"key":16,"text":17,"correct":18},"B","70%",true,{"key":20,"text":21,"correct":14},"C","90%",{"key":23,"text":24,"correct":14},"D","100%","钢筋混凝土预制桩应在混凝土达到设计强度的70%方可起吊，达到100%方可运输和打桩。如提前吊运，应采取措施并经验算合格后方可进行。桩在起吊和搬运时，吊点应符合设计要求，满足吊桩弯矩最小的原则。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]