[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893350":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893350,580,1,"单选题","地下工程的早强水泥砂浆锚杆用树脂药包的，正常温度下需要搅拌的时间为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","30s",true,{"key":16,"text":17,"correct":18},"B","45～60s",false,{"key":20,"text":21,"correct":18},"C","3min",{"key":23,"text":24,"correct":18},"D","5min","地下工程的早强水泥砂浆锚杆用树脂药包时，还应注意，搅拌时间应根据现场气温决定，20℃时固化时间为5min；温度下降5℃时固化时间约会延长一倍，即15℃时为10min，10℃时为20min。因此，地下工程在正常温度下，搅拌时间约为30s，当温度在10℃以下时，搅拌时间可适当延长为45～60s。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]