[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893335":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893335,580,1,"单选题","桥梁墩台基础施工时，在砂夹卵石层中，优先采用的主要沉桩方法为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","锤击沉桩",false,{"key":16,"text":17,"correct":18},"B","射水沉桩",true,{"key":20,"text":21,"correct":14},"C","振动沉桩",{"key":23,"text":24,"correct":14},"D","静力压桩","射水沉桩施工方法的选择应视土质情况而异，在砂夹卵石层或坚硬土层中，一般以射水为主，锤击或振动为辅；在亚黏土或黏土中，为避免降低承载力，一般以锤击或振动为主，以射水为辅，并应适当控制射水时间和水量。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]