[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893328":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893328,580,1,"单选题","钢筋混凝土预制桩锤击沉桩法施工，通常采用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","轻锤低击的打桩方式",false,{"key":16,"text":17,"correct":18},"B","重锤低击的打桩方式",true,{"key":20,"text":21,"correct":14},"C","先四周后中间的打桩顺序",{"key":23,"text":24,"correct":14},"D","先打短桩后打长桩","AB两项，钢筋混凝土预制桩锤击沉桩法施工时宜采用“重锤低击”，即锤的重量大而落距小，这样，桩锤不易产生回跃，不致损坏桩头，且桩易打入土中，效率高；反之，若“轻锤高击”，则桩锤易产生回跃，易损坏桩头，桩难以打入土中。C项，基坑不大时，打桩应从中间分头向两边或四周进行；当基坑较大时，应将基坑分为数段，而后在各段范围内分别进行。打桩应避免自外向内，或从周边向中间进行。D项，当桩的规格不同时，打桩顺序宜先大后小、先长后短。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]