[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893317":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893317,580,1,"单选题","场地平整前，确定场地平整施工方案的首要任务是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","确定场地内外土方调配方案",false,{"key":16,"text":17,"correct":14},"B","计算挖方的工程量",{"key":19,"text":20,"correct":21},"C","明确场地的设计标高",true,{"key":23,"text":24,"correct":14},"D","计算填方的工程量","首先要确定标高才能计算土方的工程量等工作",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]