[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893311":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893311,580,1,"单选题","关于钢筋混凝土预制桩加工制作，说法正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","长度在10m以上的桩必须工厂预制",false,{"key":16,"text":17,"correct":14},"B","重叠法预制不宜超过5层",{"key":19,"text":20,"correct":14},"C","重叠法预制下层桩强度达到设计强度70%时方可灌注上层桩",{"key":22,"text":23,"correct":24},"D","桩的强度达到设计强度的70%方可起吊",true,"长度小于 10m的短桩，一般多在工厂预制。制作预制桩有并列法、间隔法、重叠法、翻模法等。现场预制桩多用重叠法预制，重叠层数不宜超过 4层。上层桩或邻近桩的灌注，应在下层桩或邻近桩混凝土达到设计强度等级的 30%以后方可进行。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]