[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893308":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893308,580,1,"单选题","下列关于钻孔压浆桩施工的说法，正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","向孔内高压灌注制备好的浆液要达到没有塌孔危险的高程",true,{"key":16,"text":17,"correct":18},"B","向孔内高压灌注制备好的浆液要达到地下水位以下0.5～1.0m处",false,{"key":20,"text":21,"correct":18},"C","投放粗集料至孔口设计标高以上0.5m",{"key":23,"text":24,"correct":18},"D","在水泥浆初凝之前多次重复地向孔内补浆","钻孔压浆桩施工是利用长螺旋钻孔机钻孔至设计深度，在提升钻杆的同时通过设在钻头上的喷嘴，向孔内高压灌注制备好的以水泥浆为主剂的浆液，达到没有塌孔危险的高程或地下水位以上 0.5～1.0m处；起钻后形成水泥浆护壁孔，可向孔内放入钢筋笼，并放入至少一根直通孔底的高压注浆管，然后投放粗集料至孔口设计标高以上 0.3m；最后通过高压注浆管，在水泥浆终凝之前多次重复地向孔内补浆，直至孔口冒浆为止。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]