[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893307":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893307,580,1,"单选题","沉井高度较大时，为避免不均匀沉降，沉井制作前应（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","开挖基坑和搭设工作台",false,{"key":16,"text":17,"correct":14},"B","挖土下沉",{"key":19,"text":20,"correct":21},"C","铺设垫层、承垫木",true,{"key":23,"text":24,"correct":14},"D","抽取垫木","沉井基础施工的主要工序：测量放线、开挖基坑和搭设工作台→铺设垫层、承垫木→沉井制作→抽取垫木→挖土下沉→封底、回填、浇筑其他部分结构。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]