[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893304":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893304,580,1,"单选题","地下工程开挖后，对于软弱围岩优先选用的支护方式为（ ）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","锚索支护",false,{"key":16,"text":17,"correct":14},"B","锚杆支护",{"key":19,"text":20,"correct":14},"C","喷射混凝土支护",{"key":22,"text":23,"correct":24},"D","喷锚支护",true,"本题考查的是边坡稳定。喷锚支护是在地下工程开挖后，及时地向围岩表面喷一薄层混凝土，有时再增加一些锚杆，从而部分地阻止围岩向洞内变形，以达到支护的目的。对于软弱围岩，相当于围岩分类中的Ⅳ类和Ⅴ类围岩，一般强度低、成岩不牢固的软岩，破碎及强烈风化的岩石。该类围岩在地下工程开挖后一般都不能自稳，所以必须立即喷射混凝土，有时还要加锚杆和钢筋网才能稳定围岩。@##",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]