[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893299":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893299,580,1,"单选题","地下连续墙的施工工序包括：①开挖槽段②吊放钢筋笼③吸泥清底④筑导墙⑤水下浇筑混凝土（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","①→④→③→②→⑤",false,{"key":16,"text":17,"correct":14},"B","①→④→②→③→⑤",{"key":19,"text":20,"correct":21},"C","④→①→③→②→⑤",true,{"key":23,"text":24,"correct":14},"D","④→①→②→③→⑤","地下连续墙基本施工程序为：挖导沟→筑导墙→挖槽→吸泥清底刷壁→吊放接头管（接头箱）→吊放钢筋笼→插入混凝土导管→水下（泥浆下）浇筑混凝土→结束。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]