[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893298,580,1,"单选题","堤身较高或受地形限制时，建筑路堤的方法通常采用（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","水平分层填筑",false,{"key":16,"text":17,"correct":14},"B","竖向填筑",{"key":19,"text":20,"correct":14},"C","纵向分层填筑",{"key":22,"text":23,"correct":24},"D","混合填筑",true,"因地形限制或堤身较高时，不宜采用水平分层填筑或横向填筑法进行填筑时，可采用混合填筑法。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]