[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893284":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893284,580,1,"单选题","逆作法基础施工的大致顺序为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支护结构→中间支撑→地下室顶板浇筑→底板混凝土浇筑",true,{"key":16,"text":17,"correct":18},"B","支护结构→中间支撑→底板混凝土浇筑→地下室顶板浇筑",false,{"key":20,"text":21,"correct":18},"C","支护结构→地下室顶板浇筑→中间支撑→底板混凝土浇筑",{"key":23,"text":24,"correct":18},"D","中间支撑→支护结构→底板混凝土浇筑→地下室顶板浇筑","本题考查的是地基与基础工程施工技术。逆作法基础施工工序为：施工四周的支护结构、施工中间支撑柱和基础、浇筑地下室顶板、逐层挖土浇筑下层顶板、浇筑底板混凝土。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]