[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893273":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893273,580,1,"单选题","下列关于钢结构安装，表述正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","一般钢柱的刚性较差，吊装时通常采用双机抬吊",false,{"key":16,"text":17,"correct":18},"B","高层钢结构一般是划分多个流水作业段进行安装",true,{"key":20,"text":21,"correct":14},"C","吊车梁与牛腿用焊接，梁与制动架之间用螺栓连接",{"key":23,"text":24,"correct":14},"D","吊车梁吊装常采用自行杆式起重机，以轮胎式起重机应用最多","本题考查的是建筑工程主体结构施工技术。选项A错误，一般钢柱的刚性较好，吊装时通常采用一点起吊。常用的吊装方法有旋转法、滑行法和递送法。对于重型钢柱，也可采用双机抬吊；选项C错误，吊车梁与牛腿用螺栓连接，梁与制动架之间用高强螺栓连接；选项D错误，吊车梁吊装常采用自行杆式起重机，以履带式起重机应用最多。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]