[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893267":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893267,580,1,"单选题","柱的最后固定中，灌筑分两次进行，第一次灌注后，待混凝土强度达到（ ）设计强度后，拔去楔块再第二次灌筑混凝土至杯口顶面。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","25%",true,{"key":16,"text":17,"correct":18},"B","30%",false,{"key":20,"text":21,"correct":18},"C","70%",{"key":23,"text":24,"correct":18},"D","75%","本题考查的是建筑工程主体结构施工技术。柱的最后固定。在柱的底部四周与基础杯口的空隙之间，浇筑细石混凝土，捣固密实，使柱的底脚完全嵌固在基础内，完成柱的最后固定。灌筑分两次进行，第一次先浇至楔块底面，待混凝土强度达到25%设计强度后，拔去楔块再第二次灌筑混凝土至杯口顶面。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]