[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893246":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893246,580,1,"单选题","下列关于隧道支护的方法，表述正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","喷射混凝土支护，基本采用干喷法",false,{"key":16,"text":17,"correct":14},"B","随机锚杆支护，是对个别松动岩块随机性固定",{"key":19,"text":20,"correct":14},"C","超前预注浆支护，使开挖工作面始终在预注浆固结之前的岩层中推进",{"key":22,"text":23,"correct":24},"D","超前锚杆支护，当锚杆可能强度不够时，可改用打入钢导管注浆加固",true,"本题考查的是隧道工程施工技术。选项A错误，喷射混凝土分为干喷和湿喷，因干喷回弹和粉尘严重，一般不采用，现基本采用湿喷；选项B错误，随机锚杆是加固个别松动岩块的，随需要加固点布置；选项C错误，超前预注浆支护，使开挖工作面始终在预注浆固结过的岩层中推进。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]