[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893242,580,1,"单选题","采用明排水法开挖基坑，在基坑开挖过程中设置的集水坑应( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","布置在基础范围以内",false,{"key":16,"text":17,"correct":14},"B","布置在基坑底部中央",{"key":19,"text":20,"correct":21},"C","布置在地下水走向的上游",true,{"key":23,"text":24,"correct":14},"D","经常低于挖土面1．Om以上","集水坑应设置在基础范围以外，地下水走向的上游。根据地下水量大小、基坑平面形状及水泵能力，集水坑每隔20～40m设置一个。集水坑的直径或宽度一般为0.6～0.8m，其深度随着挖土的加深而加深，要经常低于挖土面0.7～l.Om，坑壁可用竹、木或钢筋笼等简易加固。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]