[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893240,580,1,"单选题","关于预应力后张法的施工工艺，下列说法正确的是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","灌浆孔的间距，对预埋金属螺旋管不宜大于40m",false,{"key":16,"text":17,"correct":18},"B","张拉预应力筋时，设计无规定的，构件混凝土的强度不低于设计强度等级的75%",true,{"key":20,"text":21,"correct":14},"C","对后张法预应力梁，张拉时现浇结构混凝土的龄期不宜小于5d",{"key":23,"text":24,"correct":14},"D","孔道灌浆所用水泥浆拌和后至灌浆完毕的时间不宜超过35min","灌浆孔的间距，对预理金属螺旋管不宜大于 30m。张拉预应力筋时，构件混凝土的强度应按设计规定，如设计无规定，则应不低于设计的混凝土立方体抗压强度标准值的 75%。对后张法预应力梁和板，现浇结构混凝土的龄期分别不宜小于 7d和 5d。水泥浆拌和后至灌浆完毕的时间不宜超过 30min。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]