[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893239":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893239,580,1,"单选题","预应力砼构件先张法施工工艺流程正确的为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安骨架、钢筋-张拉-安底、侧模-浇灌-养护-拆模-放张",false,{"key":16,"text":17,"correct":18},"B","安底模、骨架、钢筋-张拉-支侧模-浇灌-养护-拆模-放张",true,{"key":20,"text":21,"correct":14},"C","安骨架-安钢筋-安底、侧模-浇灌-张拉-养护-放张-拆模",{"key":23,"text":24,"correct":14},"D","安底模、侧模-安钢筋-张拉-浇灌-养护-放张-拆模","先安装低模再张拉，故 AC错。张拉后安装侧模，故 D错。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]