[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893236":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893236,580,1,"单选题","静力压桩正确的施工工艺流程为（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定位-吊桩-对中-压桩-接桩-压桩-送桩-切割桩头",true,{"key":16,"text":17,"correct":18},"B","吊桩-定位-对中-压桩-送桩-压桩-接桩-切割桩头",false,{"key":20,"text":21,"correct":18},"C","对中-吊桩-插桩-送桩-静压-接桩-压桩-切割桩头",{"key":23,"text":24,"correct":18},"D","吊桩-定位-压桩-送桩-接桩-压桩-切割桩头","静力压桩施工工艺流程：测量定位→压桩机就位→吊桩、插桩→桩身对中调制→静压沉桩→接桩（下段桩上端距地面 0.5-1m时接上段桩）→逐段重复静压沉桩和接桩→送桩→终止压桩→切割桩头。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]