[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893228":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893228,580,1,"单选题","泥浆护壁成孔灌注桩施工流程（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","测量放线定位→桩机就位→埋设护筒→成孔→一次清孔→安装导管→安装钢筋笼→二次清孔→灌注水下混凝土→起拔导管、护筒→桩头混凝土养护",false,{"key":16,"text":17,"correct":14},"B","测量放线定位→埋设护筒→桩机就位→成孔→安装钢筋笼→一次清孔→安装导管→二次清孔→起拔导管、护筒→灌注水下混凝土→桩头混凝土养护",{"key":19,"text":20,"correct":21},"C","测量放线定位→埋设护筒→桩机就位→成孔→一次清孔→安装钢筋笼→安装导管→二次清孔→灌注水下混凝土→起拔导管、护筒→桩头混凝土养护",true,{"key":23,"text":24,"correct":14},"D","测量放线定位→埋设护筒→桩机就位→成孔→一次清孔→安装钢筋笼→安装导管→灌注水下混凝土→二次清孔→桩头混凝土养护→起拔导管、护筒","",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]