[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893218":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893218,580,1,"单选题","后张法工艺流程（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安装底模→埋管制孔→安钢筋骨架、支模→浇筑混凝土→养护、拆模→抽管→清理孔道→穿筋→张拉预应力筋→孔道灌浆→起吊运输",false,{"key":16,"text":17,"correct":18},"B","安装底模→安钢筋骨架、支模→埋管制孔→浇筑混凝土→抽管→养护、拆模→清理孔道→穿筋→张拉预应力筋→孔道灌浆→起吊运输",true,{"key":20,"text":21,"correct":14},"C","安钢筋骨架、支模→安装底模→埋管制孔→浇筑混凝土→抽管→养护、拆模→清理孔道→穿筋→孔道灌浆→张拉预应力筋→起吊运输",{"key":23,"text":24,"correct":14},"D","安装底模→安钢筋骨架、支模→浇筑混凝土→埋管制孔→抽管→养护、拆模→穿筋→清理孔道→张拉预应力筋→孔道灌浆→起吊运输","后张法工艺流程为：安装底模→安钢筋骨架、支模→埋管制孔→浇筑混凝土→抽管→养护、拆模→清理孔道→穿筋→张拉预应力筋→孔道灌浆→起吊运输。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]