[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893216":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893216,580,1,"单选题","对于大跨度的焊接球节点钢管网架的吊装，一般选用（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","整体吊装法施工",true,{"key":16,"text":17,"correct":18},"B","滑移吊装法施工",false,{"key":20,"text":21,"correct":18},"C","高空拼装法施工",{"key":23,"text":24,"correct":18},"D","整体顶升法施工","本题考查的是结构吊装工程施工。大跨度结构的吊装有整体吊装法、滑移吊装法、高空拼装法、整体顶升法。整体吊装法是焊接球节点网架吊装的一种常用方法。首先在地面（单层建筑）或在网架设计位置的下层楼边上（多层建筑）将网架一次拼装成整体，然后采用吊升设备将网架整体吊升到设计位置，就位固定。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]