[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893204":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893204,580,1,"单选题","悬索桥的混凝土索塔施工采用的模板形式为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","组合模板",false,{"key":16,"text":17,"correct":14},"B","大模板",{"key":19,"text":20,"correct":14},"C","台模",{"key":22,"text":23,"correct":24},"D","滑模",true,"悬索桥混凝土索塔通常采用滑模、爬模、翻模并配以塔式起重机或泵送浇筑。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]