[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893192":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893192,580,1,"单选题","在多层及高层、高耸钢结构安装中，宜划分多个流水作业段进行安装，每节流水段内柱的分节位置宜在梁顶标高以上（ ）m处。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","0．5～1．0",false,{"key":16,"text":17,"correct":18},"B","1．0～1．3",true,{"key":20,"text":21,"correct":14},"C","1．3～1．8",{"key":23,"text":24,"correct":14},"D","1．8～2．1","高层钢结构的安装是在分片的基础上，采用综合吊装法。一般是划分多个流水作业段进行安装。划分流水作业段时应注意：各段应满足最重构件的起重能力；满足下节流水段内构件的起吊高度；段内柱的长度应适应工厂加工、运输堆放和现场吊装，一般宜为2~3个楼层高度，宜在梁顶标高以上1.0~1.3m处分节；应与混凝土结构施工相适应；每节流水段可根据结构特点和现场条件，在平面上划分流水区进行施工。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]