[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893190":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893190,580,1,"单选题","装配整体式结构中，预制构件吊装就位后，应及时校准并（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采取临时固定措施，每个预制构件的临时支撑不宜少于2道",true,{"key":16,"text":17,"correct":18},"B","采取临时固定措施，每个预制构件的临时支撑不宜少于3道",false,{"key":20,"text":21,"correct":18},"C","采取永久固定措施，每个预制构件的临时支撑不宜少于2道",{"key":23,"text":24,"correct":18},"D","采取永久固定措施，每个预制构件的临时支撑不宜少于3道","本题考查的是装配式混凝土施工。预制构件吊装就位后，应及时校准并采取临时固定措施，每个预制构件的临时支撑不宜少于两道。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]