[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892931":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892931,579,2,"多选题","在混凝土浇筑的施工过程中，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对于砂砾地基，应清除杂物，整平建基面，再浇10～20cm低强度等级的混凝土作垫层",true,{"key":16,"text":17,"correct":18},"B","焊接与绑扎接头距离钢筋弯头起点不小于9d，并不得位于最大弯矩处",false,{"key":20,"text":21,"correct":18},"C","采用高压水冲毛，一般应在浇后一两天进行",{"key":23,"text":24,"correct":14},"D","对于大体积混凝土浇筑块，成型后的偏差不应超过模板安装允许偏差的50%～100%",{"key":26,"text":27,"correct":14},"E","钢筋在调直机上调直后，其表面伤痕不得使钢筋截面面积减少5%以上","ADE","B项，机械连接接头在受压区和装配式构件中钢筋受力较小部位。焊接与绑扎接头距离钢筋弯头起点不小于10d，并不得位于最大弯矩处。C项，对施工纵缝表面可不凿毛，但应冲洗干净，以利灌浆。采用高压水冲毛，视气温高低，可在浇筑后5～20h进行；当用风砂枪冲毛时，一般应在浇后一两天进行。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]