[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892929":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892929,579,2,"多选题","关于土质边坡开挖与支护，下列说法正确的有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","边坡开挖应采取自上而下、分区、分段、分层的方法依次进行",true,{"key":16,"text":17,"correct":14},"B","坡面开挖时，应根据土质情况，间隔一定的高度设置永久性戗台",{"key":19,"text":20,"correct":14},"C","支护包括锚固、护面和支档等形式",{"key":22,"text":23,"correct":14},"D","对于不稳定边坡的开挖，尽量避免采取爆破方式施工",{"key":25,"text":26,"correct":27},"E","采用机械开挖时，应距设计坡面留有不小于25cm的保护层",false,"ABCD","A项，边坡开挖应采取自上而下、分区、分段、分层的方法依次进行，不允许先下后上切脚开挖。B项，坡面开挖时，应根据土质情况，间隔一定的高度设置永久性戗台。戗台宽度视用途而定，台面横向应为反向排水坡，同时在坡脚设置护脚和排水沟。应严格施工过程质量控制，避免超、欠挖或倒坡。C项，受施工条件等因素的制约，施工中经常会遇到不稳定边坡，应采取适当措施加以支护，以保证施工安全。支护主要有锚固、护面和支挡几种型式。D项，对于不稳定边坡的开挖，尽量避免采取爆破方式施工（冻土除外），边坡加固应及时进行。永久性高边坡加固，应按设计要求进行。E项，采用机械开挖时，应距设计坡面留有不小于20cm的保护层，最后用人工进行坡面修整。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]