[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892927":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892927,579,2,"多选题","堆石坝施工时，堆石料和砂砾石料填筑施工前，先进行碾压试验，确定（ ）等碾压施工参数。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","碾重",true,{"key":16,"text":17,"correct":14},"B","碾压遍数",{"key":19,"text":20,"correct":21},"C","碾压速度",false,{"key":23,"text":24,"correct":21},"D","含水量",{"key":26,"text":27,"correct":21},"E","限制物料直径","AB","",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]