[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892923":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892923,579,2,"多选题","关于模板的安装、拆除及支护，下列说法错误的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","立模后，混凝土浇筑前，应在模板内表面涂以脱模剂，以利拆除",false,{"key":16,"text":17,"correct":18},"B","对于承重板，混凝土强度应达到设计强度的95%才能拆模",true,{"key":20,"text":21,"correct":14},"C","磨板表面应光洁平整，接缝严密，不漏浆",{"key":23,"text":24,"correct":14},"D","提高模板使用的周转率是降低模板成本的关键",{"key":26,"text":27,"correct":18},"E","悬臂模板可设置外部拉杆，以保证模板的稳定性","BE","B项，拆模时间应根据设计要求、气温和混凝土强度增长情况而定。对非承重模板，混凝土强度应达到2.5MPa以上，其表面和棱角不因拆模而损坏方可拆除。对于承重板，要求达到规定的混凝土设计强度的百分率后才能拆模。E项，除悬臂模板外，竖向模板与内倾模板都必须设置内部撑杆或外部拉杆，以保证模板的稳定性。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]