[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892902":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892902,579,2,"多选题","关于二次设备的安装和调试，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","盘用基础槽钢埋设、二期混凝土浇筑、抹平",true,{"key":16,"text":17,"correct":18},"B","盘上所有器具、元件、继电器由试验人员或机器校验、整定及率定合格",false,{"key":20,"text":21,"correct":14},"C","立盘垂直、水平、屏间的距离、边屏、基础接地等均应按相关规范和设计要求施工",{"key":23,"text":24,"correct":14},"D","端子排安装，应注意安装单位的编号和标志",{"key":26,"text":27,"correct":18},"E","按原理图对线、盘内少量改线（1～3级）器具或单元进行试验、调试、整个回路调试、整体调试","ACD","二次设备安装归纳起来有以下内容：立盘、配线、继电器和元器件的整定、调试。具体包括：①盘用基础槽钢埋设、二期混凝土浇筑、抹平；②立盘（屏、柜），垂直、水平、屏间的距离、边屏、基础接地等均应按相关规范和设计要求施工；③盘上所有器具、元件、继电器全部由试验人员校验、整定及率定合格，主要包含各种继电器元件、信号灯、按钮、光字牌、电阻、熔丝、盘顶小母线等；④端子排安装，应注意安装单位的编号和标志；⑤将电缆头做好，注意芯线预留的长度要同盘顶一样高，对线及编号应按图纸配线，电缆与屏内设备连接必须通过端子排；⑥按原理图对线、盘内少量改线（3～5级）器具或单元进行试验、调试、整个回路调试、整体调试。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]