[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892883":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892883,579,2,"多选题","专项部分投资包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","建设征地移民补偿",true,{"key":16,"text":17,"correct":14},"B","水土保持工程投资",{"key":19,"text":20,"correct":21},"C","建筑工程投资",false,{"key":23,"text":24,"correct":14},"D","环境保护工程投资",{"key":26,"text":27,"correct":21},"E","机电设备及安装工程投资","ABD","专项部分投资：包括：建设征地移民补偿、水土保持工程投资、环境保护工程投资及其他投资。其他可根据需要计列，如水文设施工程投资，采用其他行业定额编制的供电设施工程投资，穿越铁路、公路等专项工程投资。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]