[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892877":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892877,579,2,"多选题","根据工程实际情况可单独列示的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","缆机平台",true,{"key":16,"text":17,"correct":18},"B","施工交通",false,{"key":20,"text":21,"correct":14},"C","掘进机泥水处理系统",{"key":23,"text":24,"correct":18},"D","施工房屋建筑",{"key":26,"text":27,"correct":14},"E","管片预制系统土建设施","ACE","其他施工临时工程。其他施工临时工程指除施工导流、施工交通、施工场外供电、施工房屋建筑、缆机平台、掘进机泥水处理系统和管片预制系统土建设施以外的施工临时工程。其他施工临时工程主要包括施工供水（大型泵房及干管）、砂石料系统、混凝土拌和浇筑系统、大型机械安装拆卸、防汛、防冰、施工排水、施工通信等工程。根据工程实际情况可单独列示缆机平台、掘进机泥水处理系统和管片预制系统土建设施等项目。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]