[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892874":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892874,579,2,"多选题","下列关于设备原价的说法中，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","国产设备的原价为其出厂价",true,{"key":16,"text":17,"correct":18},"B","进口设备以到岸价为原价",false,{"key":20,"text":21,"correct":14},"C","进口设备以到岸价和进口征收的税金、手续费、商检费及港口费等各项费用之和为原价",{"key":23,"text":24,"correct":18},"D","大型机组及其他大型设备分瓣运至工地后的拼装费用，不包括在设备原价内",{"key":26,"text":27,"correct":14},"E","大型机组及其他大型设备分瓣运至工地后的拼装费用，应包括在设备原价内","ACE","A项，国产设备，其原价指出厂价；BC两项，进口设备，以到岸价和进口征收的税金、手续费、商检费及港口费等各项费用之和为原价；DE两项，大型机组及其他大型设备分瓣运至工地后的拼装费用，应包括在设备原价内。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]