[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892864":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892864,579,2,"多选题","投标人填入工程量清单中的单价应包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","直接费",true,{"key":16,"text":17,"correct":18},"B","间接费",false,{"key":20,"text":21,"correct":14},"C","施工管理费",{"key":23,"text":24,"correct":14},"D","利润",{"key":26,"text":27,"correct":14},"E","税金","ACDE","投标人填入工程量清单中的单价应包括直接费（人工费、材料费、机械使用费和季节、夜间、高原、风沙等原因增加的直接费）、施工管理费、企业利润和税金，并考虑风险因素等的全部费用。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]