[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892863":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892863,579,2,"多选题","以质量为单位计算工程量的金属结构设备或装置性材料有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","闸门",true,{"key":16,"text":17,"correct":14},"B","拦污栅",{"key":19,"text":20,"correct":21},"C","启闭机",false,{"key":23,"text":24,"correct":14},"D","埋件",{"key":26,"text":27,"correct":14},"E","高压钢管","ABDE","以质量为单位计算工程量的金属结构设备或装置性材料，如闸门、拦污栅、埋件、高压钢管等，按招标图示尺寸计算的有效质量计量。运输、加工及安装过程中的操作损耗所发生的费用，应摊入有效工程量的工程单价中。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]