[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892859":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892859,579,2,"多选题","机电主要设备安装工程项目组成内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","大型泵站水泵",true,{"key":16,"text":17,"correct":14},"B","大型泵站电动机",{"key":19,"text":20,"correct":21},"C","起重设备",false,{"key":23,"text":24,"correct":21},"D","电流互感器",{"key":26,"text":27,"correct":14},"E","励磁系统","ABE","机电主要设备安装工程项目组成内容：包括水轮机设备安装（水泵一水轮机）、大型泵站水泵、调速器及油压装置、发电机（发电机一电动机）、大型泵站电动机、励磁系统、主阀、桥式起重机、主变压器等设备，均由设备本体和附属设备及埋件组成。CD两项属于机电其他设备安装工程项目组成内容。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]