[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892858":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892858,579,2,"多选题","预应力混凝土中（ ）所占用的空间体积不予扣除。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","钢筋",true,{"key":16,"text":17,"correct":18},"B","螺丝",false,{"key":20,"text":21,"correct":14},"C","锚索",{"key":23,"text":24,"correct":14},"D","钢管",{"key":26,"text":27,"correct":14},"E","埋件","ACDE","膜袋混凝土、预应力混凝土按招标设计图示尺寸计算的有效实体方体积计量。预应力混凝土中钢筋、锚索、钢管、钢构件、埋件等所占用的空间体积不予扣除。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]