[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892855":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892855,579,2,"多选题","生产准备费包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","生产及管理单位提前进厂费",true,{"key":16,"text":17,"correct":14},"B","生产职工培训费",{"key":19,"text":20,"correct":14},"C","管理用具购置费",{"key":22,"text":23,"correct":24},"D","生产人员工资",false,{"key":26,"text":27,"correct":14},"E","工器具及生产家具购置费","ABCE","生产准备费包括： ①生产及管理单位提前进厂费：按一至四部分建筑安装工程量的0.1%～0.3%计算；改扩建与加固工程、河道堤防及疏浚工程原则上不计此项费用。 ②生产职工培训费：按一至四部分建筑安装工作量的0.3%～0.5%计算；枢纽及引水工程取大值，其他工程取小值。 ③管理用具购置费：按工程一至四部分建筑安装工作量的0.05%～0.08%计算；枢纽及引水工程取大值，其他水利工程取中值或低值。 ④工器具及生产家具购置费：按占设备费的0.1%～0.2%计算。枢纽及引水工程取下限，其他工程取中限、上限。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]