[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892851":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892851,579,2,"多选题","完工结算与竣工决算的主要区别有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","范围",true,{"key":16,"text":17,"correct":18},"B","计算方法",false,{"key":20,"text":21,"correct":14},"C","成本内容",{"key":23,"text":24,"correct":18},"D","完成的人员",{"key":26,"text":27,"correct":18},"E","准确性","AC","完工结算与竣工决算的主要区别有两点：一是范围，完工结算的范围只是承包工程项目，是基本建设项目的局部，而竣工决算的范围是基本建设项目的整体；二是成本内容，完工结算只是承包合同范围内的预算成本，而竣工决算是完整的预算成本，它还要计入工程建设的其他费用开支，水库淹没处理、水土保持及环境保护工程费用和建设期融资利息等工程成本和费用。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]