[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892850":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892850,579,2,"多选题","以下属于生产准备工作的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","招收和培训人员",true,{"key":16,"text":17,"correct":18},"B","技术交底",false,{"key":20,"text":21,"correct":14},"C","生产技术准备",{"key":23,"text":24,"correct":14},"D","生产物资准备",{"key":26,"text":27,"correct":14},"E","制定必要的管理制度","ACDE","在施工过程中，建设单位应当根据建设项目的生产技术特点，按时组成专门班子，有计划有步骤地做好各项生产准备，为竣工后投产创造条件。生产准备工作主要有生产组织准备、招收和培训人员、生产技术准备、生产物资准备、正常的生活福利设施准备、制定必要的管理制度和安全生产操作规程等。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]