[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892848":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892848,579,2,"多选题","对于某些大型工程和重要的中型工程一般采用，三阶段设计包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","初步设计",true,{"key":16,"text":17,"correct":18},"B","技术设计",false,{"key":20,"text":21,"correct":14},"C","招标设计",{"key":23,"text":24,"correct":18},"D","施工方案设计",{"key":26,"text":27,"correct":14},"E","施工图设计","ACE","设计工作是分阶段进行的，一般采用两阶段进行，即初步设计与施工图设计。对于某些大型工程和重要的中型工程一般采用三阶段设计，即初步设计、招标设计及施工图设计。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]