[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892844":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892844,579,2,"多选题","施工临时供电线路工程量可按设计的（ ）计算。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","线路走向",true,{"key":16,"text":17,"correct":18},"B","电流等级",false,{"key":20,"text":21,"correct":14},"C","电压等级",{"key":23,"text":24,"correct":18},"D","电阻等级",{"key":26,"text":27,"correct":14},"E","回路数","ACE","施工临时公路的工程量可根据相应设计阶段施工总平面布置图或设计提出的运输线路分等级计算公路长度或具体工程量。施工临时供电线路工程量可按设计的线路走向、电压等级和回路数计算。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]