[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892840":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892840,579,2,"多选题","根据《水利工程工程量清单计价规范》（GB 50501—2007），以“m2”为计量单位的项目有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","岩石层帷幕灌浆",false,{"key":16,"text":17,"correct":14},"B","岩石层固结灌浆",{"key":19,"text":20,"correct":21},"C","回填灌浆",true,{"key":23,"text":24,"correct":21},"D","岩石面喷浆",{"key":26,"text":27,"correct":21},"E","混凝土地下连续墙","CDE","",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]