[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892839":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892839,579,2,"多选题","关于疏浚工程的设计工程量计算，下列说法正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","疏浚工程量计算宜按设计水下方计量",true,{"key":16,"text":17,"correct":18},"B","吹填工程量计算只需考虑吹填区填筑量",false,{"key":20,"text":21,"correct":14},"C","疏浚与吹填工程提供给造价专业的疏浚与吹填工程量计量单位均应为水下方",{"key":23,"text":24,"correct":18},"D","多个疏浚区只需计算总工程量",{"key":26,"text":27,"correct":14},"E","取土区土质变化较大，应按地质柱状剖面图分别计算各类土的工程量","ACE","关于疏浚工程设计工程量计算的原则及方法应符合下列规定：①疏浚工程量的计算，宜按设计水下方计量，开挖过程中的超挖及回淤量不应计入；②吹填工程量计算，除考虑吹填区填筑量，还应考虑吹填土层固结沉降、吹填区地基沉降和施工期泥沙流失等因素。计量单位为水下方；③疏浚与吹填工程的定额计量单位为水下方，提供给造价专业的疏浚与吹填工程量计量单位均应为水下方；④对有多个疏浚区与吹填区的工程应分别计算各分区工程量与总工程量；⑤疏浚区或取土区的土质变化较大，应按地质柱状剖面图分别计算各类土的工程量。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]