[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892835":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892835,579,2,"多选题","根据《水利水电工程标准文件》中的合同条款，承包人可同时获得工期补偿和费用补偿，但是不能获得利润补偿的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","施工过程发现文物古迹",true,{"key":16,"text":17,"correct":18},"B","异常恶劣气候条件",false,{"key":20,"text":21,"correct":14},"C","承包人遇到不利物质条件",{"key":23,"text":24,"correct":18},"D","发包人原因引起暂停施工",{"key":26,"text":27,"correct":18},"E","发包人提供的材料设备不符合合同要求","AC","B项，异常恶劣气候条件，承包人只能获得工期补偿。D项，发包人原因引起暂停施工，承包人可以同时获得工期补偿、费用补偿和利润补偿。E项，发包人提供的材料设备不符合合同要求，承包人可以同时获得工期补偿、费用补偿和利润补偿。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]