[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892833":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892833,579,2,"多选题","关于工程预付款支付的说法，正确的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","第一次预付款应在协议书签订后14d内，由承包人向发包人提交经发包人认可的预付款保函，并经监理工程师出具付款凭证书报送发包人批准后予以支付",false,{"key":16,"text":17,"correct":18},"B","保函金额为本次预付款金额",true,{"key":20,"text":21,"correct":18},"C","第二次预付款需待承包人主要设备进入工地后，其估算值已达到本次预付款金额时",{"key":23,"text":24,"correct":18},"D","工程预付款保函在预付款被发包人扣回前一直有效",{"key":26,"text":27,"correct":14},"E","第二次预付支付时，发包人收到监理工程师出具的付款证书后28d内支付给承包人","BCD","第一次预付款应在协议书签订后21d内，由承包人向发包人提交经发包人认可的预付款保函，并经监理工程师出具付款凭证书报送发包人批准后予以支付。第二次预付款需待承包人主要设备进入工地后，其估算值已达到本次预付款金额时，由承包人提出书面申请，经监理工程师核实后出具付款证书报给发包人，发包人收到监理工程师出具的付款证书后14d内支付给承包人。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]