[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892829":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892829,579,2,"多选题","一般情况下，不允许索赔的费用包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","承包人的索赔准备费用",true,{"key":16,"text":17,"correct":14},"B","索赔事项引起的工程计划调整费用",{"key":19,"text":20,"correct":14},"C","工程保险费用",{"key":22,"text":23,"correct":24},"D","承包商对索赔事项采取减轻措施而损失的费用",false,{"key":26,"text":27,"correct":14},"E","索赔金额在索赔处理期间的利息","ABCE","一般情况下，不允许索赔的费用包括：①承包人的索赔准备费用；②工程保险费用；③因合同变更或索赔事项引起的工程计划调整、分包合同修改等费用；④因承包人的不适当行为而扩大的损失；⑤索赔金额在索赔处理期间的利息。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]