[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892828":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892828,579,2,"多选题","完工结算资料包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","工程竣工报告及工程竣工验收单",true,{"key":16,"text":17,"correct":14},"B","承包商与项目法人签订的工程合同或协议书",{"key":19,"text":20,"correct":14},"C","施工图纸",{"key":22,"text":23,"correct":24},"D","工程概算",false,{"key":26,"text":27,"correct":14},"E","采用的预算定额、材料价格、基础单价及其他费用标准","ABCE","完工结算资料包括以下几部分： ①工程竣工报告及工程竣工验收单。 ②承包商与项目法人签订的工程合同或协议书。 ③施工图纸、设计变更通知书、现场变更签证及现场记录。 ④采用的预算定额、材料价格、基础单价及其他费用标准。 ⑤施工图预算。 ⑥其他有关资料。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]