[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-892827":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},892827,579,2,"多选题","进度付款申请单应包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","截至本次付款周期初已实施工程的价款",false,{"key":16,"text":17,"correct":18},"B","根据合同约定应增加和扣减的变更金额",true,{"key":20,"text":21,"correct":18},"C","根据合同约定应增加和扣减的索赔金额",{"key":23,"text":24,"correct":18},"D","根据合同约定应支付的预付款和扣减的返还预付款",{"key":26,"text":27,"correct":18},"E","根据合同约定应扣减的质量保证金","BCDE","进度付款申请单应包括下列内容：①截至本次付款周期末已实施工程的价款。②根据合同约定应增加和扣减的变更金额。③根据合同约定应增加和扣减的索赔金额。④根据合同约定应支付的预付款和扣减的返还预付款。⑤根据合同约定应扣减的质量保证金。⑥根据合同约定应增加和扣减的其他金额。",{"id":6,"name":31,"category":32,"favorite":33},"[水利工程]建设工程计量与计价实务","建筑工程",0]